Detailed design stage in building design
Detailed design is sometimes referred to as 'developed design' or 'definition'. It is the process of taking on and developing the approved concept design.
By the end of the detailed design process, the design should be dimensionally correct and co-ordinated, describing all the main components of the building and how they fit together. However, technical aspects of the design may require further development, design by specialists may not yet have been fully incorporated into the design and it will not have been packaged for tender.
Detailed design should provide sufficient information for applications for statutory approval to be made.
Detailed design should include:
- Overall layout.
- Road layouts and landscape.
- Operational flows and departmental operational policies.
- Horizontal and vertical circulation routes, including accessibility requirements.
- Schedules of accommodation, including occupancy numbers for each space.
- Identification of standard and non-standard room layouts.
- If appropriate, room data sheets.
- Building dimensions and gridlines.
- Architectural plans sections and elevations of buildings, parts of buildings and components, including:
- Block plans.
- Site plans and external works.
- Changes in floor levels.
- Expansion joints.
- Demarcation of changes to finishes.
- Reflected ceiling plans.
- Outline specification including schedules of components, defining the performance and/or material standards required (including colours).
- Elements of design that require specialist input or early choice of manufacturer. Designers should investigate suppliers certificates, warranties and compliance with standards.
- Requirements for mock-ups, testing, samples or models necessary to satisfy performance or public relations requirements (including computer generated images).
- Key assemblies, component drawings and schedules with special attention to junctions and interfaces between elements which will influence the structural or services designs or have an effect on the spatial allowances. Key details will include:
- External walls, lining, cladding, glazing, windows and blinds.
- Balconies, canopies and entrances.
- Roofing and finishes, rooflights, drainage, gutters and outlets.
- Floor constructions and finishes.
- Staircases.
- Damp proof courses.
- Service duct and services plan enclosures.
- Load bearing internal walls and partitions, including lifts and other shafts.
- Non-load bearing partitions.
- Ceiling construction and support.
- Overall dimensions and fixing details for fixed equipment such as sanitary fittings and joinery.
- Roads, paths, paving, boundaries and retaining walls.
- External gradients and falls including gutters and outlets.
- Components that can be standardised, mass produced or prefabricated, resulting in reduced costs or reduced construction durations.
- Initial schedules indicating:
- The location of all structural elements in relation to gridlines.
- Dimensions and sizes of beams, columns, walls and slabs.
- Sketch details of junctions and proposed fixings.
- Superimposed loading allowances for each floor slab.
- The proposed discipline for all holes giving range and sizes permissible.
- An outline specification including total weights of reinforcement.
- The detailed design should highlight any changes from the concept design and provide the services engineer with sufficient information to undertake the services design.
- Building services plans, sections and elevations showing:
- Plumbing and drainage (high and low level).
- Ductwork.
- Heavy pipework.
- Electrical trunking.
- Light pipework.
- Electrical control wiring.
- Radiators.
- Plantroom layouts.
- Riser drawings.
- Access requirements and builders work in connection.
- Define phases if the project is to be phased. This can be complicated by items that appear in buildings intended for later phases, but that are required for the operation of earlier phases, for example boilers or escape stairs.
- Safety strategy.
- Fire strategy, including:
- Zoning and compartmentation.
- Separation (such as fire resistance of compartments, restriction of openings between compartments and distances to boundaries).
- Protected shafts (staircases and services).
- Surface spread of flame and escape strategy (including travel distances and staircase widths).
- Active measures such as detection, ventilation, alarms, sprinklers.
- Minimum ventilation requirements where no mechanical ventilation is provided.
- Dry risers and hose reels.
- Uninterrupted power supplies.
- Fire rated cables.
- Acoustic separation and acoustic conditions (reverberation times etc).
- The use of materials and the potential for re-use, recycling and waste handling (see site waste management plan).
- Detailed cost plan showing the capital and lifecycle costs for all the components.
- Risk assessment including operational issues such as; lifts (goods / passenger / fire and other equipment that may require a lifting certificate and cleaning cradles), cleaning of atrium roofs and facade etc.
[edit] Related articles on Designing Buildings
- Block plan.
- Briefing documents.
- Client.
- Concept design.
- Concept architectural design.
- Concept architectural design checklist.
- Demystifying design processes of architectural details.
- Design.
- Design phase.
- Design process essentials.
- Design quality.
- Design review.
- Design risk management.
- Detailed design report.
- Detailed services design.
- Detailed structural design.
- Location plan.
- Project performance management.
- Stakeholders.
- Structural design.
- User panels.
- Value management.
- Whole life costs.
[edit] External references
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.